Financial Services·Tier-2 retail bank, Accra

From 12 physical servers to 3: a Ghanaian retail bank cuts its IT bill by two-thirds

The problem

Twelve aging physical servers running in a branch-headquarter closet — monthly electricity and cooling cost of GH₵ 18,000, no disaster recovery, 6-hour restore time, and two hardware failures in 18 months.

What we did

We consolidated the workloads onto three modern hosts running VMware vSphere, configured HA clusters, introduced snapshot-based backups to a remote site in Kumasi, and wrote a live-migration runbook the bank's own admins could execute.

"Flash Code's team embedded with ours for six weeks. They didn't just virtualize the servers — they taught our admins how to own the platform after they left."

Head of Infrastructure, client bank

How we delivered it

  1. Step 1Discovery

    Full workload inventory and dependency map over two weeks on-site.

  2. Step 2Design

    Right-sized three hosts with N+1 capacity and dual 10GbE for live migration.

  3. Step 3Pilot

    Migrated the non-critical workloads first to prove the runbook before banking hours.

  4. Step 4Cutover

    Weekend migration window with rollback to original hardware if anything failed.

  5. Step 5Handover

    Two-week shadow period and a runbook every admin could read without training.